Meetings / Dec 21, 2022 / Item 102

Item 102

approved grant

Dec 21, 2022

Description

Authorize to award a grant to Warner Village Water District, in the amount not to exceed $538,215, for the Wastewater Treatment Facility (WWTF) Rapid Infiltration Basin System and Plant Process Upgrade project. Effective upon G&C approval through December 31, 2024. 100% Federal Funds. (2) Further authorize a loan agreement with Warner Village Water District, in an amount not to exceed $1,259,834 to finance the WWTF Rapid Infiltration Basin System and Plant Process Upgrade project. Effective upon G&C approval. 100% CWSRF Repayment Funds.

Amount
$1.3M
$538,215,, $1,259,834
Funding Source
100% Federal Funds; 100% CWSRF Repayment Funds
Vote Record approved
Motion by Kenney, seconded by Wheeler acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_102.pdf Open in new tab →
← Back to Dec 21, 2022 meeting