Meetings / Dec 7, 2022 / Item 25

Item 25

approved contract

Dec 7, 2022

Description

Authorize the Bureau of Construction to enter into a contract with Beck & Bellucci, Inc., Franklin, NH, on the basis of a low bid of $1,163,079.37 for deck replacement of Red List Bridge carrying NH 103 over I-89 NB in Warner (Project: Warner 40622). (2) Further authorize that a 10% contingency in the amount of $116,307.94 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through October 27, 2023. 100% Other Funds.

Amount
$1.2M
$1,163,079.37, $116,307.94
Vendor
Beck & Bellucci, Inc.
Franklin, NH
Funding Source
10% contingency in the amount of; 100% Other Funds
Vote Record approved
Motion by Stevens, seconded by Kenney acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_25.pdf Open in new tab →
← Back to Dec 7, 2022 meeting