Meetings / Dec 22, 2021 / Item 112

Item 112

approved contract

Dec 22, 2021

Description

Authorize to amend an existing sole source contract with Blake Group Holding Inc., d/b/a Blake Equipment, Concord, NH (originally approved by G&C on 7-14-21, item #52), for boiler and steam system maintenance and repair services by extending the completion date from December 31, 2021 to June 30, 2023, and by increasing the price by $39,901 from $23,308.16 to $63,209.16. 66% General, 34% Transfer from other Agency Funds.

Amount
$63,209
$39,901, $23,308.16, $63,209.16
Funding Source
66% General; 34% Transfer from other Agency Funds
Effective Dates
December 31, 2021 — June 30, 2023
Vote Record approved
Motion by Wheeler, seconded by Kenney acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_112.pdf Open in new tab →