Item 12
approved nominationOct 27, 2021
Description
Authorize to amend the existing contract with the contractor The Alternative Life Center as listed in bold and detailed in letter dated September 12, 2021, to cover additional costs for a court-appointed consultant while the organization undergoes receivership to determine the viability of the organization and to bring in new leadership by increasing the total price by $70,000 from $18,709,274 to $18,779,274 with no change to the contract completion date of June 30, 2022. 100% General Funds.
Amount
$18.8M
$70,000, $18,709,274, $18,779,274
Funding Source
100% General Funds
Vote Record
approved
Motion by Warmington, seconded by Stevens
Joseph Kenney
(R)
yes
Cinde Warmington
(D)
yes
Janet Stevens
(R)
yes
Ted Gatsas
(R)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_12.pdf