Meetings / Sep 15, 2021 / Item 83

Item 83

approved contract late item

Sep 15, 2021

Description

Authorize the Division of Public Works Design and Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for the Manchester Anti-Terrorism/Force Protection REBID, Manchester, NH, for a total price not to exceed $1,694,000. (2)Further authorize a contingency in the amount of $140,000 for unanticipated modifications, bringing the total to $1,834,000. (3)Further authorize the amount of $68,600 for payment to the Department of Administrative Services, Division of Public Works Design and Construction, for engineering services provided, bringing the total to $1,902,600. Effective upon G&C approval through May 9, 2022. 100% Capital-Federal Funds.

Amount
$1.9M
$1,694,000, $140,000, $1,834,000, $68,600, $1,902,600
Vendor
R.S. Audley Inc.
Bow, NH
Funding Source
100% Capital
Vote Record approved
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_83.pdf Open in new tab →