Meetings / Jun 16, 2021 / Item 46

Item 46

approved contract late item

Jun 16, 2021

Description

Authorize the Bureau of Highway Design to amend a contract with Stantec Consulting Services Inc., Edmonton, Alberta, Canada, and Bedford, NH (originally approved by G&C on 12-6-17, item #10), for Part B2 preliminary and final design of improvements to the Craftsman Lane/Boston Post Road and NH 101A from Boston Post Road to Continental Boulevard intersections in the Town of Merrimack, by increasing the total amount by $51,364.44 from $461,469.18 to $512,833.62, and by extending the completion date from December 31, 2021 to December 31, 2022, for additional final design services that were more complex than anticipated in the original scope of work. Effective upon G&C approval. 100% Federal Funds.

Amount
$512,834
$51,364.44, $461,469.18, $512,833.62
Funding Source
100% Federal Funds
Effective Dates
December 31, 2021 — December 31, 2022
Vote Record approved
Motion by Wheeler, seconded by Kenney acted as follows
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_46.pdf Open in new tab →
← Back to Jun 16, 2021 meeting