Meetings / Jun 2, 2021 / Item 12

Item 12

approved contract late item

Jun 2, 2021

Description

Authorize to enter into a sole source amendment to an existing contract with Johnson Controls Inc., Manchester, NH (originally approved by G&C on 4-11-18, tabled item #10), for the application of Belzona coating to condenser tube sheets, end bells and water boxes in two York Chillers to protect against rust buildup, by increasing the price by $51,060 from $100,000 to $151,060 with no change to the completion date of June 30, 2021. 100% General Funds.

Amount
$151,060
$51,060, $100,000, $151,060
Department
DEPARTMENT OF HEALTH AND HUMAN SERVICES
New Hampshire Hospital
Vendor
Johnson Controls Inc.
Manchester, NH
Funding Source
100% General Funds
Vote Record approved
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_12.pdf Open in new tab →
← Back to Jun 2, 2021 meeting