Item 40
approved contract late itemJun 2, 2021
Description
Authorize the Bureau of Construction to enter into a contract with F.L. Merrill Construction Inc., Loudon, NH, for culvert replacement under NH 107 in Northwood, on the basis of a low bid of $425,184.50. (2)Further authorize a contingency in the amount of $42,518.45 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through November 12, 2021. 100% Other Funds.
Amount
$425,184
$425,184.50, $42,518.45
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Other Funds
Vote Record
approved
Joseph Kenney
(R)
yes
Cinde Warmington
(D)
yes
Janet Stevens
(R)
yes
Ted Gatsas
(R)
yes
Dave Wheeler
(R)
yes
Documents (1)