Meetings / Jan 22, 2021 / Item 33

Item 33

approved contract late item

Jan 22, 2021

Description

Authorize the Bureau of Construction to enter into a contract with Renaud Bros., Inc., Vernon, VT, for the Cornish-Windsor covered bridge scour mitigation, on the basis of a low bid of $993,755. (2)Further authorize a contingency in the amount of $99,375.50 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 29, 2021. 100% Federal Funds.

Amount
$993,755
$993,755, $99,375.50
Vendor
Renaud Bros., Inc.
Vernon, VT
Funding Source
100% Federal Funds
Vote Record approved
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes