Item 33
approved contract late itemJan 22, 2021
Description
Authorize the Bureau of Construction to enter into a contract with Renaud Bros., Inc., Vernon, VT, for the Cornish-Windsor covered bridge scour mitigation, on the basis of a low bid of $993,755. (2)Further authorize a contingency in the amount of $99,375.50 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 29, 2021. 100% Federal Funds.
Amount
$993,755
$993,755, $99,375.50
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Joseph Kenney
(R)
yes
Cinde Warmington
(D)
yes
Janet Stevens
(R)
yes
Ted Gatsas
(R)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_33.pdf