approved contract late item

Jan 22, 2021

Description

Authorize the Bureau of Construction to enter into a contract with Liddell Brothers Inc., Halifax, MA, for curve warning signs improvements on State highways, on the basis of a low bid of $315,247.50. (2)Further authorize a contingency in the amount of $18,914.85 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through September 24, 2021. 100% Federal Funds.

Amount
$315,248
$315,247.50, $18,914.85
Vendor
Liddell Brothers Inc.
Halifax, MA
Funding Source
100% Federal Funds
Vote Record approved
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes