Meetings / Jan 22, 2021 / Item 49

Item 49

approved contract late item

Jan 22, 2021

Description

Authorize the Bureau of Construction to enter into a contract with J. Hutchins Inc., Richmond, VT, for roadway resurfacing in 2 towns in District 1, on the basis of a low bid of $1,877,388.94. (2)Further authorize a contingency in the amount of $93,869.45 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through September 17, 2021. 100% Federal Funds.

Amount
$1.9M
$1,877,388.94, $93,869.45
Vendor
J. Hutchins Inc.
Richmond, VT
Funding Source
100% Federal Funds
Vote Record approved
Joseph Kenney (R) yes
Cinde Warmington (D) yes
Janet Stevens (R) yes
Ted Gatsas (R) yes
Dave Wheeler (R) yes

Documents (1)

Item_49.pdf Open in new tab →
← Back to Jan 22, 2021 meeting