Meetings / Oct 21, 2020 / Item 19

Item 19

approved contract

Oct 21, 2020

Description

Authorize the Bureau of Construction to enter into a contract amendment with J.P. Sicard Inc., Barton, VT (originally approved by G&C on 6-10-20, item #30), for roadway slope repair on NH 16 in Errol, by increasing the amount by $43,346.25 from $1,069,513 to $1,112,859.25. Effective upon G&C approval. 100% Federal Funds.

Amount
$1.1M
$43,346.25, $1,069,513, $1,112,859.25
Funding Source
100% Federal Funds
Vote Record approved
Motion by Prescott, seconded by Cryans acted as follows
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes