Item 14A
approved contractAug 27, 2025
Description
Authorize the Bureau of Construction to enter into a contract with William P Davis Excavation, LLC, Hampton, NH, on the basis of a sole bid received of $2,897,831, for a rail trail improvement project along the former Hampton Branch Railroad corridor extending the northerly to the North Hampton/Hampton town line. (2) Further authorize a contingency in the amount of $289,783.10, for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through November 21, 2025, unless amended by the Department in accordance with the Standard Specifications. 100% Federal Funds
Amount
$2.9M
$2,897,831,, $289,783.10
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Kenney, seconded by Liot Hill acted as follows
Joseph Kenney
(R)
yes
Karen Liot Hill
(D)
yes
Janet Stevens
(R)
yes
John Stephen
(R)
yes
Dave Wheeler
(R)
yes
Related Sub-Items (6)
14
Authorize to accept and place on file the Bureau of Environment’s annual accounting of permit fees and in lieu mitigation fees made to the Department of Environmental Services pursuant to RSA 482-A an
approved
14
Authorize to accept and place on file the Bureau of Environment’s annual accounting of permit fees and in lieu mitigation fees made to the Department of Environmental Services pursuant to RSA 482-A an
approved
14
Authorize to accept and place on file the Bureau of Environment’s annual accounting of permit fees and in lieu mitigation fees made to the Department of Environmental Services pursuant to RSA 482-A an
approved
14B
Authorize the Bureau of Construction to enter into a contract with Sargent Corporation, Orono, ME, on the basis of a low bid of $4,599,905, for installation of median barrier on I-95 starting at mile
$4.6M
approved
14B
Authorize the Bureau of Construction to enter into a contract with Sargent Corporation, Orono, ME, on the basis of a low bid of $4,599,905, for installation of median barrier on I-95 starting at mile
$4.6M
approved
14B
Authorize the Bureau of Construction to enter into a contract with Sargent Corporation, Orono, ME, on the basis of a low bid of $4,599,905, for installation of median barrier on I-95 starting at mile
$4.6M
approved
Documents (3)
Item_14.pdf
Open in new tab →
Item_14A.pdf
(14A)
Open in new tab →
Item_14B.pdf
(14B)
Open in new tab →