Meetings / Jun 24, 2020 / Item 59

Item 59

approved contract late item

Jun 24, 2020

Description

Authorize the Bureau of Construction to enter into a contract with Alvin J. Coleman & Son Inc., Conway, NH, for culvert rehab and replacement in Shelburne, NH, on the basis of a low bid of $596,376.75. (2)Further authorize a contingency in the amount of $59,637.68 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through June 18, 2021. 100% Federal Funds.

Amount
$596,377
$596,376.75, $59,637.68
Vendor
Alvin J. Coleman & Son Inc.
Conway, NH
Funding Source
100% Federal Funds
Vote Record approved
Motion by Cryans, seconded by Volinsky
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes

Documents (1)

Item_59.pdf Open in new tab →
← Back to Jun 24, 2020 meeting