approved contract

Apr 8, 2020

Description

Authorize the Bureau of Construction to enter into a contract with Pike Industries Inc., Belmont, NH, for approximately 25 miles of pavement resurfacing and repair along NH 101 between Epping and Exeter, on the basis of a low bid of $6,981,484.59. (2)Further authorize a contingency in the amount of $349,074.23 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through July 30, 2021. 100% Federal Funds.

Amount
$7.0M
$6,981,484.59, $349,074.23
Vendor
Pike Industries Inc.
Belmont, NH
Funding Source
100% Federal Funds
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes