Meetings / Mar 25, 2020 / Item 24

Item 24

approved contract

Mar 25, 2020

Description

Authorize the Bureau of Construction to enter into a contract with C.L.H. & Son Inc., Auburn, ME, for culvert repair under the I-93 northbound off ramp to I-89 in Bow, on the basis of a low bid of $289,663.75. (2)Further authorize a contingency in the amount of $28,966.38 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through August 28, 2020. 96.5% Turnpike, 3.5% Private Local Funds.

Amount
$289,664
$289,663.75, $28,966.38
Vendor
C.L.H. & Son Inc.
Auburn, ME
Funding Source
96.5% Turnpike; 3.5% Private Local Funds
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes

Documents (1)

Item_24.pdf Open in new tab →
← Back to Mar 25, 2020 meeting