Meetings / Mar 11, 2020 / Item 25

Item 25

approved contract

Mar 11, 2020

Description

Authorize the Bureau of Construction to enter into a contract with R.M. Piper Inc., Plymouth, NH, for bridge preservation work on 3 bridges in Plymouth and Campton, NH, on the basis of a low bid of $1,729,083.50. (2)Further authorize a contingency in the amount of $172,908.35 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 16, 2020. 100% Federal Funds.

Amount
$1.7M
$1,729,083.50, $172,908.35
Vendor
R.M. Piper Inc.
Plymouth, NH
Funding Source
100% Federal Funds
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes

Documents (1)

Item_25.pdf Open in new tab →