Authorize the Division of Public Works Design and Construction to enter into a contract amendment with Structuretone LLC, Boston, MA (originally approved by G&C on 7-19-17, item #128), to establish an allowance increase for Steam Conversion, Dolloff, Spaulding and Medical and Surgical Buildings, Concord, NH, by increasing the amount by $24,500 from $2,097,524.94 to $2,122,024.94, and by extending the completion date of May 1, 2018 to April 30, 2020. 100% General Funds.

Amount
$2.1M
$24,500, $2,097,524.94, $2,122,024.94
Funding Source
100% General Funds
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes