approved contract late item

Feb 19, 2020

Description

Authorize the Bureau of Construction to enter into a contract with E.D. Swett Inc., Concord, NH, for bridge preservation work in Boscawen, NH, on the basis of a low bid of $1,647,611.50. (2)Further authorize a contingency in the amount of $164,761.15 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 23, 2020. 100% Other Funds (Betterment Funds).

Amount
$1.6M
$1,647,611.50, $164,761.15
Vendor
E.D. Swett Inc.
Concord, NH
Funding Source
100% Other Funds (Betterment Funds)
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes