Meetings / Jan 22, 2020 / Item 83

Item 83

approved contract

Jan 22, 2020

Description

Authorize to enter into a sole source amendment to a current contract with Powerhouse Equipment & Engineering Co., Inc., Delanco, NJ (originally approved by G&C on 4-11-18, item #106), for portable steam boiler rental services, by increasing the amount by $99,840 from $836,820 to $936,660, and by extending the completion date from January 31, 2020 to April 30, 2020. 100% General Funds.

Amount
$936,660
$99,840, $836,820, $936,660,
Funding Source
100% General Funds
Effective Dates
January 31, 2020 — April 30, 2020
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes