Item 127
approved contract late itemDec 18, 2019
Description
Authorize to execute a sole source amendment to the agreement with The H.L. Turner Group Inc., Concord, NH (originally approved by G&C on 11-14-18, item #56), to provide a condition assessment of certain elements of Murphy Dam in Pittsburg, NH, by increasing the contract by $198,283.47 from $219,016.69 to $417,300.16 to allow for the execution of repairs critical to the safe operation of the dam and completion of the condition assessment under the original agreement, and by extending the completion date to December 31, 2021 from December 31, 2019. 100% Connecticut-Coos Project (Other).
Amount
$417,300
$198,283.47, $219,016.69, $417,300.16
Department
DEPARTMENT OF ENVIRONMENTAL SERVICES
Funding Source
100% Connecticut
Vote Record
approved
Motion by Cryans, seconded by Pignatelli acted as follows
Michael Cryans
(D)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Ted Gatsas
(R)
yes
Debora Pignatelli
(D)
yes
Documents (1)
Item_127.pdf
Open in new tab →