Item 202
approved contract late itemDec 18, 2019
Description
Authorize the Division of Public Works Design and Construction to enter into a contract with Glover Plumbing & Heating Services, Barrington, NH, for the temporary Boiler Removal at the Department of Justice, Concord, NH, for a total price not to exceed $222,188. (2)Further authorize a contingency in the amount of $22,218 for unanticipated expenses, bringing the total to $244,406. Effective upon G&C approval through July 31, 2020. 100% Capital-General Funds.
Amount
$244,406
$222,188, $22,218, $244,406
Department
DEPARTMENT OF ADMINISTRATIVE SERVICES
Funding Source
100% Capital
Vote Record
approved
Motion by Cryans, seconded by Volinsky acted as follows
Michael Cryans
(D)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Ted Gatsas
(R)
yes
Debora Pignatelli
(D)
yes
Documents (1)
Item_202.pdf
Open in new tab →