approved contract

Nov 6, 2019

Description

Authorize the Bureau of Construction to enter into a contract with E.D. Swett Inc., Concord, NH, for bridge rehabilitation efforts on I-89 NB, SB bridges over US Route 4 at Exit 19 and associated ramp work and bridge preservation work on the I-89 NB, SB bridges over the Mascoma River, on the basis of a low bid of $9,764,986. (2)Further authorize a contingency in the amount of $488,249.30 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 14, 2022. 51.2% General, 48.8% Federal Funds.

Amount
$9.8M
$9,764,986, $488,249.30
Vendor
E.D. Swett Inc.
Concord, NH
Funding Source
51.2% General; 48.8% Federal Funds
Vote Record approved
Motion by Gatsas, seconded by Prescott
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes