Meetings / Aug 28, 2019 / Item 27

Item 27

approved late item

Aug 28, 2019

Description

Authorize the Bureau of Aeronautics to provide funding to the City of Concord, NH, to conduct a terminal area study for the Concord Municipal Airport, in the amount of $104,081. Effective upon G&C approval through June 21, 2022. 95% Federal, 5% General Funds.

Amount
$104,081
$104,081
Funding Source
95% Federal; 5% General Funds
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes
Related Sub-Items (20)
27A
Authorize the Division of Operations to accept and expend revenue in the amount of $30,000 from the NH Division of Homeland Security for FEMA – Public Assistance Alternative Procedures for Direct Admi
$30,000 approved
27A
Authorize the Division of Operations to accept and expend revenue in the amount of $30,000 from the NH Division of Homeland Security for FEMA – Public Assistance Alternative Procedures for Direct Admi
$30,000 approved
27A
Authorize the Division of Operations to accept and expend revenue in the amount of $30,000 from the NH Division of Homeland Security for FEMA – Public Assistance Alternative Procedures for Direct Admi
$30,000 approved
27A
Authorize the Division of Operations to accept and expend revenue in the amount of $30,000 from the NH Division of Homeland Security for FEMA – Public Assistance Alternative Procedures for Direct Admi
$30,000 approved
27A
Authorize the Division of Operations to accept and expend revenue in the amount of $30,000 from the NH Division of Homeland Security for FEMA – Public Assistance Alternative Procedures for Direct Admi
$30,000 approved
27B
Authorize the Bureau of Bridge Design to amend the Interstate Bridge Agreement with the State of Maine to allow the Department to reimburse Maine for NH’s portion of the increased construction costs a
$9.5M approved
27B
Authorize the Bureau of Bridge Design to amend the Interstate Bridge Agreement with the State of Maine to allow the Department to reimburse Maine for NH’s portion of the increased construction costs a
$9.5M approved
27B
Authorize the Bureau of Bridge Design to amend the Interstate Bridge Agreement with the State of Maine to allow the Department to reimburse Maine for NH’s portion of the increased construction costs a
$9.5M approved
27B
Authorize the Bureau of Bridge Design to amend the Interstate Bridge Agreement with the State of Maine to allow the Department to reimburse Maine for NH’s portion of the increased construction costs a
$9.5M approved
27B
Authorize the Bureau of Bridge Design to amend the Interstate Bridge Agreement with the State of Maine to allow the Department to reimburse Maine for NH’s portion of the increased construction costs a
$9.5M approved
27C
Authorize the Bureau of Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for reconstruction of I-93 NB and SB from the Massachusetts State Line through Exit 1, on the basis of a l
$19.4M approved
27C
Authorize the Bureau of Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for reconstruction of I-93 NB and SB from the Massachusetts State Line through Exit 1, on the basis of a l
$19.4M approved
27C
Authorize the Bureau of Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for reconstruction of I-93 NB and SB from the Massachusetts State Line through Exit 1, on the basis of a l
$19.4M approved
27C
Authorize the Bureau of Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for reconstruction of I-93 NB and SB from the Massachusetts State Line through Exit 1, on the basis of a l
$19.4M approved
27C
Authorize the Bureau of Construction to enter into a contract with R.S. Audley Inc., Bow, NH, for reconstruction of I-93 NB and SB from the Massachusetts State Line through Exit 1, on the basis of a l
$19.4M approved
27D
Authorize the Bureau of Construction to enter into a contract with Weaver Brothers Construction Company Inc., Bow, NH, for interstate rehabilitation on I-89, on the basis of a low bid of $14,899,945.2
$14.9M approved
27D
Authorize the Bureau of Construction to enter into a contract with Weaver Brothers Construction Company Inc., Bow, NH, for interstate rehabilitation on I-89, on the basis of a low bid of $14,899,945.2
$14.9M approved
27D
Authorize the Bureau of Construction to enter into a contract with Weaver Brothers Construction Company Inc., Bow, NH, for interstate rehabilitation on I-89, on the basis of a low bid of $14,899,945.2
$14.9M approved
27D
Authorize the Bureau of Construction to enter into a contract with Weaver Brothers Construction Company Inc., Bow, NH, for interstate rehabilitation on I-89, on the basis of a low bid of $14,899,945.2
$14.9M approved
27D
Authorize the Bureau of Construction to enter into a contract with Weaver Brothers Construction Company Inc., Bow, NH, for interstate rehabilitation on I-89, on the basis of a low bid of $14,899,945.2
$14.9M approved

Documents (5)

Item_27.pdf Open in new tab →
Item_27A.pdf (27A) Open in new tab →
Item_27B.pdf (27B) Open in new tab →
Item_27C.pdf (27C) Open in new tab →
Item_27D.pdf (27D) Open in new tab →
← Back to Aug 28, 2019 meeting