Meetings / Jul 10, 2019 / Item 24B

Item 24B

approved contract

Jul 10, 2019

Description

Authorize the Bureau of Construction to enter into a contract with C.L.H & Son Inc., Auburn, ME, for rehabilitation of four large metal culverts along US 3 (Bypass) in Gilford, on the basis of a low bid of $1,068,762.50. (2)Further authorize a contingency in the amount of $53,438.13 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through November 8, 2019. 100% Federal Funds.

Amount
$1.1M
$1,068,762.50, $53,438.13
Vendor
C.L.H & Son Inc.
Auburn, ME
Funding Source
100% Federal Funds
Vote Record approved
Motion by Volinsky, seconded by Prescott acted as follows
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes
Related Sub-Items (6)

Documents (2)

Item_24A.pdf (24A) Open in new tab →
Item_24B.pdf (24B) Open in new tab →
← Back to Jul 10, 2019 meeting