Meetings / Jun 19, 2019 / Item 96

Item 96

approved contract late item

Jun 19, 2019

Description

Authorize the Bureau of Highway Design to amend a contract with McFarland-Johnson Inc., Concord, NH, and Binghamton, NY (originally approved by G&C on 11-20-13, item #123), to prepare the second phase of the preliminary engineering design for the section of Interstate 93 passing through Bow and Concord from I-89 through I-393, by increasing the amount by $159,206.94 from $1,746,896.71 to $1,906,103.65 for additional design services, and by extending the completion date from June 30, 2019 to June 30, 2020.. Effective upon G&C approval. 100% Turnpike Funds.

Amount
$1.9M
$159,206.94, $1,746,896.71, $1,906,103.65
Vendor
McFarland-Johnson Inc.
Concord, NH
Funding Source
100% Turnpike Funds
Effective Dates
June 30, 2019 — June 30, 2020
Vote Record approved
Motion by Volinsky, seconded by Prescott acted as follows
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes

Documents (1)

Item_96.pdf Open in new tab →
← Back to Jun 19, 2019 meeting