Meetings / May 1, 2019 / Item 25

Item 25

approved contract late item

May 1, 2019

Description

Authorize the Bureau of Construction to enter into a contract with Stephens Marquis Associates Inc., Merrimack, NH, for new gasoline and diesel UST system at the Merrimack Shed, on the basis of a low bid of $646,000. (2)Further authorize a contingency in the amount of $32,300 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through August 30, 2019. 100% Underground Fuel Tank Replacement – Capital Fund.

Amount
$646,000
$646,000, $32,300
Vendor
Stephens Marquis Associates Inc.
Merrimack, NH
Funding Source
100% Underground Fuel Tank Replacement
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes

Documents (1)

Item_25.pdf Open in new tab →
← Back to May 1, 2019 meeting