approved contract late item

Apr 17, 2019

Description

Authorize to retroactively amend a sole source agreement with Inter-Fluve Inc. (originally approved by G&C on 6-22-11, item #96), to complete the Geomorphology-Based Restoration Design and Permitting for the Suncook River and Floodplain project, by extending the completion date to December 31, 2023 from December 31, 2018; changing the scope of services and contract price and method of payment to include two additional tasks, four sub-tasks and payments; and by increasing the amount by $101,800 from $991,121 to $1,092,921. 100% Capital (General) Funds.

Amount
$1.1M
$101,800, $991,121, $1,092,921
Funding Source
100% Capital (General) Funds
Vote Record approved
Motion by Cryans, seconded by Volinsky acted as follows
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes