Meetings / Apr 17, 2019 / Item 97

Item 97

approved amendment late item

Apr 17, 2019

Description

Authorize to retroactively amend the agreement with F.L. Merrill Construction Inc., Loudon, NH (originally approved by G&C on 9-13-17, item #65), to complete construction services on the Suncook River Mitigation Project, by extending the completion date to December 31, 2023 from December 31, 2018 and by reducing the amount by $19,699 from $2,636,427 to $2,616,728. 100% Capital (General) Funds.

Amount
$2.6M
$19,699, $2,636,427, $2,616,728
Vendor
F.L. Merrill Construction Inc.
Loudon, NH
Funding Source
100% Capital (General) Funds
Vote Record approved
Motion by Cryans, seconded by Volinsky acted as follows
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes