Meetings / Jan 23, 2019 / Item 40

Item 40

approved contract

Jan 23, 2019

Description

Authorize the Bureau of Construction to enter into a contract with J.P. Sicard Inc., Barton, VT, for reconstructing railway-highway crossing, roadway approaches and protective devices on US 302 in Bartlett, on the basis of a low bid of $828,633. (2)Further authorize a contingency in the amount of $66,290.64 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through June 14, 2019. 100% Federal Funds.

Amount
$828,633
$828,633, $66,290.64
Vendor
J.P. Sicard Inc.
Barton, VT
Funding Source
100% Federal Funds
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes

Documents (1)

Item_40.pdf Open in new tab →
← Back to Jan 23, 2019 meeting