Meetings / Jan 23, 2019 / Item 44

Item 44

approved contract

Jan 23, 2019

Description

Authorize the Bureau of Construction to enter into a contract with Northeast Earth Mechanics Inc., Pittsfield, NH, for replacing a structurally deficient hybrid culver that carries Batchelder Brook under NH Route 11 in Alton, on the basis of a low bid of $358,449.40. (2)Further authorize a contingency in the amount of $35,844.94 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 25, 2019. 100% Other Funds (Betterment Funds).

Amount
$358,449
$358,449.40, $35,844.94
Vendor
Northeast Earth Mechanics Inc.
Pittsfield, NH
Funding Source
100% Other Funds (Betterment Funds)
Vote Record approved
Michael Cryans (D) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Ted Gatsas (R) yes
Debora Pignatelli (D) yes

Documents (1)

Item_44.pdf Open in new tab →