Item 70
approved contract late itemDec 19, 2018
Description
Authorize the Division of Public Works Design and Construction to enter into a contract with D.L. King & Associates Inc., Nashua, NH, for the Elevator Upgrade at NH State Men’s Prison, Concord, NH, for a total price not to exceed $713,685. (2)Further authorize a contingency in the amount of $43,815 for unanticipated expenses, bringing the total to $757,500. (3)Further authorize the amount of $15,000 for payment to the Department of Administrative Services, Division of Public Works Design and Construction, Capital Clerk for oversight and engineering services provided, bringing the total to $772,500. Effective upon G&C approval through October 25, 2019. 100% Capital – General Funds.
Amount
$772,500
$713,685, $43,815, $757,500, $15,000, $772,500
Department
DEPARTMENT OF ADMINISTRATIVE SERVICES
Funding Source
100% Capital
Vote Record
approved
Motion by Kenney, seconded by Volinsky acted as follows
Joseph Kenney
(R)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_70.pdf
Open in new tab →