Authorize the Bureau of Bridge Design to amend a sole source contract with Kleinfelder Northeast Inc., Manchester, NH (originally approved by G&C on 9-7-16, item #18), for the preliminary design for the replacement of the Red List bridge carrying NH Route 101 over Pulpit Brook in the Town of Bedford, by increasing the amount by $156,562.82 from $165,918.18 to $322,481 for additional design services, and by extending the completion date from December 31, 2018 to December 31, 2019. 100% Federal Funds.

Amount
$322,481
$156,562.82, $165,918.18, $322,481
Vendor
Kleinfelder Northeast Inc.
Manchester, NH
Funding Source
100% Federal Funds
Effective Dates
December 31, 2018 — December 31, 2019
Vote Record approved
Joseph Kenney (R) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_31.pdf Open in new tab →