Item 43
approved contractOct 31, 2018
Description
Authorize the Bureau of Construction to enter into a contract with Pike Industries Inc., Belmont, NH, for resurfacing approximately 13.5 miles along NH 28, on the basis of a low bid of $5,308,013.40. (2)Further authorize a contingency in the amount of $265,400.67 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through September 13, 2019. 100% Federal Funds.
Amount
$5.3M
$5,308,013.40, $265,400.67
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Joseph Kenney
(R)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes
Related Sub-Items (2)
43A
Authorize the Bureau of Highway Maintenance to enter into a lease agreement with Nortrax Inc., Pembroke, NH, with credit financing through Deere Credit Inc., Johnston, IA, for 66 loader backhoes on th
$5.2M
approved
43A
Authorize the Bureau of Highway Maintenance to enter into a lease agreement with Nortrax Inc., Pembroke, NH, with credit financing through Deere Credit Inc., Johnston, IA, for 66 loader backhoes on th
$5.2M
approved
Documents (1)
Item_43.pdf
Open in new tab →