Item 20
approved contractJun 25, 2025
Description
Authorize the Bureau of Construction to retroactively extend the completion date of Project: Manchester #44501 from May 16, 2025 to June 25, 2025. (2) Further authorize to retroactively increase the contract value amount with C.W. Sliter & Sons, LLC d/b/a CWS Fence & Guardrail Co., Andover, NH by $216,000 from $1,446,755 to $1,662,755 for guardrail removal and replacement on I-293 through the Millyard in Manchester, NH. Effective upon G&C approval. 100% Turnpike Funds
Amount
$1.7M
$216,000, $1,446,755, $1,662,755
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Turnpike Funds
Effective Dates
May 16, 2025 — June 25, 2025
Vote Record
approved
Motion by Kenney, seconded by Stevens acted as follows
Joseph Kenney
(R)
yes
Karen Liot Hill
(D)
yes
Janet Stevens
(R)
yes
John Stephen
(R)
yes
Dave Wheeler
(R)
yes