Item 83
approved contractSep 20, 2018
Authorize the Division of Public Works Design and Construction to increase the DPW fees in the amount of $63,900, $42,300 for Project 80929T, for Paint & Carpentry, Howard Rec, Philbrook, Philbrook Rec, and Pond Place, and $21,600 for Project 80929Q, for the Thayer, Johnson and Londergan Buildings. This will revise the total amount to $130,900 for additional engineering services for these two (2) Steam Conversion projects, for which the Division of Public Works Design and Construction is providing oversight. (2)Further authorize to establish a contingency amount provided in contract 80929T, with Project Resource Group LLC, for the Paint & Carpentry, Howard Rec, Philbrook, Philbrook Rec, and Pond Place in the amount of $60,000 for a revised total of $140,000 to cover the cost of unforeseen conditions. 100% General Funds.