Meetings / Aug 22, 2018 / Item 20

Item 20

approved contract

Aug 22, 2018

Description

Authorize the Bureau of Construction to enter into a contract with Weaver Bros. Construction Co., Inc., Bow, NH, for widening NH 106 from 800’ south of Mudgett Hill Road to 1,400’ north of the NH Motor Speedway South Entrance, on the basis of a low bid of $2,631,812.60. (2)Further authorize a contingency in the amount of $184,266.88 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through November 22, 2019. 100% Federal Funds.

Amount
$2.6M
$2,631,812.60, $184,266.88
Funding Source
100% Federal Funds
Vote Record approved
Joseph Kenney (R) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes