Item 23
approved contractAug 8, 2018
Description
Authorize the Bureau of Construction to enter into a contract amendment with R.S. Audley Inc., Bow, NH (originally approved by G&C on 2-21-18, item #16), for replacement of the Mill Street Bridge over the NHRR in the Town of Haverhill, by increasing the amount by $132,000 from $1,176,845.50 to $1,308,845.50. 100% Federal Funds.
Amount
$1.3M
$132,000, $1,176,845.50, $1,308,845.50
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Prescott, seconded by Kenney acted as follows
Joseph Kenney
(R)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes