approved amendmentJun 6, 2018
Description
Authorize to execute a retroactive amendment to the agreement with F.L. Merrill Construction Inc., Loudon, NH (originally approved by G&C on 9-13-17, item #65), to complete construction services on the Suncook River Mitigation Project, by extending the completion date to December 31, 2018 from April 30, 2018. 61% Capital (General), 39% Transfer from DOT Funds.
Department
DEPARTMENT OF ENVIRONMENTAL SERVICES
Funding Source
61% Capital (General); 39% Transfer from DOT Funds