Meetings / Feb 7, 2018 / Item 57

Item 57

approved contract

Feb 7, 2018

Description

Authorize the Division of Public Works Design and Construction to enter into a contract with Turnstone Corp., Milford, NH, for the Milford Circuit Court, Milford, NH, for a total price not to exceed $4,555,300. Effective upon G&C approval through February 1, 2019. 100% General Capital Funds. (2)Further authorize a contingency in the amount of $313,838 for unanticipated structural expenses for the Milford Court, bringing the total to $4,869,138. 100% Operating–General Funds. (3)Further authorize the amount of $65,000 for payment to the Department of Administrative Services, Division of Public Works Design and Construction clerk for oversight and engineering services provided, bringing the total to $4,934,138. 100% Capital-General Funds.

Amount
$4.9M
$4,555,300, $313,838, $4,869,138, $65,000, $4,934,138
Vendor
Turnstone Corp.
Milford, NH
Funding Source
100% General Capital Funds; 100% Operating; 100% Capital
Vote Record approved
Motion by Prescott, seconded by Pappas acted as follows
Joseph Kenney (R) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_57.pdf Open in new tab →