Meetings / Dec 20, 2017 / Item 36

Item 36

approved contract

Dec 20, 2017

Description

Authorize the Bureau of Construction to enter into a contract with Miller Construction Inc., Windsor, VT, for bridge preservation work on four bridges on NH 11 and NH 103 over the Sugar River in Sunapee, on the basis of a low bid of $1,777,558.15. (2)Further authorize a contingency in the amount of $177,755.82 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 19, 2018. 100% Federal Funds.

Amount
$1.8M
$1,777,558.15, $177,755.82
Vendor
Miller Construction Inc.
Windsor, VT
Funding Source
100% Federal Funds
Vote Record approved
Motion by Kenney, seconded by Pappas acted as follows
Joseph Kenney (R) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_36.pdf Open in new tab →