Item 34
approved contract late itemJul 19, 2017
Description
Authorize the Bureau of Construction to enter into a contract with Pike Industries Inc., Belmont, NH, for pavement preservation on I-89 in Bow, Concord and Hopkinton, on the basis of a low bid of $4,059,045.68. (2)Further authorize a contingency in the amount of $202,952.28 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through July 13, 2018. 100% Federal Funds.
Amount
$4.1M
$4,059,045.68, $202,952.28
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Joseph Kenney
(R)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_34.pdf
Open in new tab →