Item 75

approved contract late item

Jun 21, 2017

Description

Authorize the Bureau of Construction to enter into a contract with Pike Industries Inc., Belmont, NH, for resurfacing 17 miles in four Tier-2 roadway segments in the southeastern region of the State, on the basis of a low bid of $6,772,056.90. (2)Further authorize a contingency in the amount of $338,602.85 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through November 3, 2017. 100% Federal Funds.

Amount
$6.8M
$6,772,056.90, $338,602.85
Vendor
Pike Industries Inc.
Belmont, NH
Funding Source
100% Federal Funds