Item 75
approved contract late itemJun 21, 2017
Description
Authorize the Bureau of Construction to enter into a contract with Pike Industries Inc., Belmont, NH, for resurfacing 17 miles in four Tier-2 roadway segments in the southeastern region of the State, on the basis of a low bid of $6,772,056.90. (2)Further authorize a contingency in the amount of $338,602.85 for payment of latent conditions, which may appear during the construction of the project. Effective upon G&C approval through November 3, 2017. 100% Federal Funds.
Amount
$6.8M
$6,772,056.90, $338,602.85
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Wheeler, seconded by Kenney
Joseph Kenney
(R)
yes
Andru Volinsky
(D)
yes
Russell Prescott
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes
Documents (1)
Item_75.pdf
Open in new tab →