approved contract

Feb 15, 2017

Description

Authorize the Bureau of Construction to enter into a contract with Weaver Bros., Construction Company Inc., Bow, NH, for reconstruction of I-93 northbound and southbound, on the basis of a low bid of $34,221,205.20. (2)Further authorize a contingency in the amount of $1,026,636.16 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through August 2, 2019. 100% Federal Funds.

Amount
$34.2M
$34,221,205.20, $1,026,636.16
Funding Source
100% Federal Funds
Vote Record approved
Motion by Prescott, seconded by Wheeler
Joseph Kenney (R) yes
Andru Volinsky (D) yes
Russell Prescott (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes