Item 36

approved contract late item

Nov 18, 2016

Description

Authorize the Bureau of Construction to enter into a contract with B.U.R. Construction LLC, Claremont, NH, for installation of scour countermeasures on the Cresson Covered Bridge in Swanzey and the Ashuelot Covered Bridge in Winchester, on the basis of a low bid of $686,950. (2)Further authorize a contingency in the amount of $34,347.50 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through September 29, 2017. 80% Federal, 20% Other Funds.

Amount
$686,950
$686,950, $34,347.50
Vendor
B.U.R. Construction LLC
Claremont, NH
Funding Source
80% Federal; 20% Other Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_36.pdf Open in new tab →