approved contract late itemNov 18, 2016
Description
Authorize the Bureau of Construction to enter into a contract with Weaver Bros. Construction Co., Inc., Bow, NH, for replacing a deteriorated 9’ by 5’ reinforced concrete box culvert carrying NH Route 11A over West Alton Brook Gilford, on the basis of a low bid of $669,520.25. (2)Further authorize a contingency in the amount of $33,476.01 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through November 17, 2017. 100% Federal Funds.
Amount
$669,520
$669,520.25, $33,476.01
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved