Meetings / Nov 18, 2016 / Item 39

Item 39

approved contract late item

Nov 18, 2016

Description

Authorize the Bureau of Construction to enter into a contract with Austin Construction Inc., Concord, VT, for replacing the structurally deficient bridge carrying NH 145 over Bishop Brook in Stewartstown, on the basis of a low bid of $1,398,236.80. (2)Further authorize a contingency in the amount of $97,876.58 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through June 15, 2018. 100% Federal Funds.

Amount
$1.4M
$1,398,236.80, $97,876.58
Vendor
Austin Construction Inc.
Concord, VT
Funding Source
100% Federal Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_39.pdf Open in new tab →