Meetings / Sep 7, 2016 / Item 39

Item 39

approved amendment

Sep 7, 2016

Description

Authorize to amend the agreement with Gannett Fleming Inc., Camp Hill, PA (originally approved by G&C on 5/27/15, item #105), to provide additional engineering analysis for four state-owned dams according to National Resource Conservation Service guidelines, by increasing the amount by $5,200 from $765,156.53 to $770,356.53, and by extending the end date to February 28, 2017 from October 31, 2016. 100% Dam Maintenance Funds.

Amount
$770,357
$5,200, $765,156.53, $770,356.53
Vendor
Gannett Fleming Inc.
Camp Hill, PA
Funding Source
100% Dam Maintenance Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes

Documents (1)

Item_39.pdf Open in new tab →