Meetings / Aug 3, 2016 / Item 23

Item 23

approved contract

Aug 3, 2016

Description

Authorize the Bureau of Construction to enter into a contract with Weaver Bros. Construction Co., Inc., Bow, NH, for pavement preservation from North Main Street to the end of I-393 in the City of Concord and the Town of Pembroke, on the basis of a low bid of $10,649,300.08. (2)Further authorize a contingency in the amount of $532,465 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 13, 2017. 100% Federal Funds.

Amount
$10.6M
$10,649,300.08, $532,465
Funding Source
100% Federal Funds
Vote Record approved
Joseph Kenney (R) yes
Colin Van Ostern (D) yes
Christopher Sununu (R) yes
Christopher Pappas (D) yes
Dave Wheeler (R) yes
Related Sub-Items (2)

Documents (1)

Item_23A.pdf (23A) Open in new tab →
← Back to Aug 3, 2016 meeting