Item 21
approved contract late itemJun 15, 2016
Description
Authorize the Bureau of Construction to enter into a contract with Weaver Brothers Construction Co Inc., Bow, NH, for constructing a modern single lane roundabout at the intersection of NH Route 9 and Base Hill Road in Keene, on the basis of a low bid of $1,482,837.70. (2)Further authorize a contingency in the amount of $103,798.64 for payment of latent conditions which may appear during the construction of the project. Effective upon G&C approval through October 14, 2016. 100% Federal Funds.
Amount
$1.5M
$1,482,837.70, $103,798.64
Department
DEPARTMENT OF TRANSPORTATION
Funding Source
100% Federal Funds
Vote Record
approved
Motion by Sununu, seconded by Pappas
Joseph Kenney
(R)
yes
Colin Van Ostern
(D)
yes
Christopher Sununu
(R)
yes
Christopher Pappas
(D)
yes
Dave Wheeler
(R)
yes